ATEF Group of Companies, by order of Ukrhydroenergo, has manufactured and supplied another block transformer with a capacity of 10 MVA and a voltage of 165 / 10.5 kV.
Under the guidance of ATEF specialists, the installation supervision and commissioning of the above-mentioned block transformer at the Srednedneprovskaya HPP in the Dnipropetrovsk region of Ukraine was completed.